§ 20-1522. Temporary mobile towers.  


Latest version.
  • Personal wireless service antennas located upon a temporary mobile tower used on an interim basis until a permanent site is constructed or located shall require the processing of an administrative permit and shall comply with the following standards:

    (1)

    The height of the tower shall not exceed 90 feet including trailer platform.

    (2)

    Temporary mobile towers shall maintain the setbacks as contained in section 20-1505. The setback shall be maintained from the trailer platform.

    (3)

    Temporary mobile towers shall be prohibited in residential zoning districts.

    (4)

    Temporary mobile towers shall have a minimum tower design windload of 80 miles per hour and shall comply with the requirements in section 20-1508.

    (5)

    A temporary mobile tower may be permitted for up to 120 days. Towers located on a site longer than this time shall require the processing of an interim use permit subject to section 20-381.

    (6)

    Temporary mobile towers shall require a building permit and comply with section 20-1516.

    (7)

    Mobile units shall have the opportunity to appeal the administrative decision subject to section 20-1517.

    (8)

    Mobile units shall not interfere with public safety telecommunications subject to section 20-1520.

(Ord. No. 275, § 2, 10-13-97)